BELGRADE, MT (August 20,
2020). The Bozeman Yellowstone International Airport will contribute $3 million
toward the construction of the Belgrade Waste Water Treatment Facility Project
scheduled to begin construction this year. City engineers calculated the
Airport’s water & sewer use to be 7.5% of the City’s total usage.
Therefore, the Gallatin Airport Authority Board, the governing body of the
Airport, agreed to pay 7.5% of the total cost of the $40 million upgrade.